EDSA road repairs resume November 20; motorists warned of weekend lane closures
ASM, Philippine Canadian Inquirer
November 20, 2026

Photo courtesy: Philippine News Agency
MANILA, Philippines — Motorists traveling along Epifanio de los Santos Avenue (EDSA) should expect possible traffic delays this weekend as the Department of Public Works and Highways (DPWH) resumes rehabilitation work along several northbound and southbound sections of the major Metro Manila highway.
The second phase of the EDSA Rehabilitation Project will resume at 10:00 PM on Friday, November 20, with repair activities continuing around the clock throughout the weekend.
Temporary lane closures will affect five road sections, including areas near SM Megamall, Ortigas, Santolan, NEPA Q-Mart and North Avenue. All affected lanes are scheduled to reopen by 5:00 AM on Monday, November 23.

Photo courtesy: Department of Public Works and Highways
Which EDSA sections will be affected?
According to the DPWH advisory, three northbound sections and two southbound sections will undergo repairs.
Northbound:
- SM Megamall near EDSA-Shaw to Ortigas-Greenhills
- White Plains Avenue to Santolan
- Santolan to NEPA Q-Mart
Southbound:
- Roosevelt Bus Station to EDSA Unioil-Bansalangin
- EDSA Unioil-Bansalangin to North Avenue Bus Station
The closures will be temporary and limited to the affected portions of the highway rather than the entire length of EDSA.
Repairs to continue throughout the weekend
The rehabilitation project involves road improvements such as concrete reblocking and asphalt overlay to repair deteriorating pavement and improve driving conditions.
Under previous weekend repair schedules, the DPWH kept unaffected lanes open to traffic while construction crews worked on designated sections.
Motorists have been advised to exercise caution near construction sites, observe traffic signs and consider alternative routes to avoid delays.
The DPWH has also clarified that the EDSA Busway remains reserved for authorized buses despite ongoing rehabilitation activities. Private vehicles must follow designated lane restrictions and traffic advisories.
EDSA rehabilitation targeted for completion by 2028
The latest construction schedule forms part of the government’s broader effort to rehabilitate EDSA, one of Metro Manila’s busiest transport corridors.
The project began under a revised implementation plan in December 2025, with rehabilitation activities divided into phases to help manage construction and minimize traffic disruptions.
The government initially considered a rehabilitation plan costing approximately P17 billion. The revised approach reduced the estimated cost to around P6 billion, according to earlier project reports.
The DPWH has been carrying out road repairs in stages, with previous work covering portions of Caloocan, Quezon City, San Juan and Mandaluyong.
Public Works Secretary Giovanni Lopez previously said the rehabilitation was intended to provide motorists and commuters with safer, better-maintained roads while keeping the highway operational during construction.
The department targets the completion of the overall rehabilitation project by late 2027 or early 2028.
For the latest round of repairs, the immediate deadline remains 5:00 AM on Monday, November 23, when all affected lanes are expected to reopen to motorists.